In 2008 Oracle acquired Primavera Software, Inc., a leading provider of Project Portfolio Management (PPM) solutions for project-intensive industries.Primavera P6 Enterprise Project Portfolio Management is an integrated project portfolio management (PPM) solution comprising role-specific functionality to satisfy each team member's needs, responsibilities, and skills. It provides a single solution for managing projects of any size, adapts to various levels of complexities within a project, and intelligently scales to meet the needs of various roles, functions, or skill levels in your organization and on your project team.Oracle Primavera P6 Version 8: Project and Portfolio Management aims to show you all the features and functionality of the software thoroughly and clearly.With Oracle Primavera P6 Version 8: Project and Portfolio Management, readers will master the core concepts of Primavera P6 and the new features associated with version 8.This book is divided into two sections, in the first section we learn the fundamental concepts behind managing projects which include organizing projects, adding activities and relationships, assigning roles and resources, scheduling a project, and much more. In the second section we cover portfolio management and how to make the best use of the web client that includes working with portfolios, portfolio analysis, portfolio capacity planning, ROI, tracking performance, and lots more.
Table of Contents (25 chapters)
Oracle Primavera P6 Version 8: Project and Portfolio Management
Credits
About the Authors
About the Reviewers
www.PacktPub.com
Preface
Index

Resource assignments


In order to appear when using the project-level filter, a resource or role must be assigned to an activity. A schedule in which all relevant activities have roles or resources assigned is called a resource loaded schedule. Resource loading is necessary when you want to utilize the resource availability analysis tools, as described in Chapter 16. It is also necessary if you want to use any of the status using tools such as E-Mail or the Progress Reporter module, or if you want to use the mobile solutions such as Team Member on the iPhone, iPad, or Android devices. Assigning resources to activities also allows personal data to show accurately in the Personal Workspace Dashboard.

Note

If you assign resources or roles in Resource Planning, as per Chapter 16, those resources or roles are still not considered in the project.

Let's start with a project that has no resources, in fact the project schedule for writing this book. We have an activity to write Chapter 6. Currently...