Exam Essentials
Describe the project management plan. The project management plan is the final, approved, documented plan that’s used in the Executing and Monitoring and Controlling phases to measure project progress.
Describe the elements of a change management process. The elements of a change management process include identifying and documenting the change (using templates and a change log), evaluating the impact, obtaining approval from the CCB, implementing the change, validating the change, updating the project management plan documents, and communicating as needed.
Explain the purpose of a CCB. The change control board reviews, approves, denies, or delays change requests.
Be able to name the types of common project changes. The types of project changes include timeline, funding, risk events, requirements, quality, resource, and scope changes.
Be able to name the types of organizational change. The types of organizational change include business merger, acquisition, demerger...