B. Tasks with zero float are critical path tasks, and if delayed, they will cause the delay of the project completion date. For more information, please see Chapter 5.
B. Remote and in-house resources are categorized as personnel management activities in the CompTIA objectives. For more information, please see Chapter 6.
A. A weighted scoring model is a tool that weights evaluation criteria and provides a way to score vendor responses. Bidder conferences, IFB, and SOW are all used during vendor solicitation. For more information, please see Chapter 9.
A, C, F. The five stages of team development are forming, storming, norming, performing, and adjourning. For more information, please see Chapter 6.
A. This describes a projectized organization because the project manager works in a division whose sole responsibility is project management, and once the team members are assigned to the project, the project manager has the authority to hold them accountable...