The CompTIA Project+ Study Guide, Second Edition is your comprehensive resource for taking Exam PK0-004. With 100% coverage of all exam objectives, this book gives you everything you need to approach the exam with confidence. Detailed explanations and superior study tools cover and reinforce setup, initiation, planning, execution, delivery, change, control, communication, and closure, and the author Kim Heldman's twenty-five years of project management experience provide deep insight into real-world applications. The book contains detailed explanations and superior study tools that cover and reinforce all the exam objectives. You’ll begin by tackling questions related to pre-project setup and project initiation. Then you’ll solve questions about creating a project charter and planning it. You’ll also take questions about developing schedules and budgets and project execution. The later chapters provide questions on managing change, control, and communication. Finally, you’ll be given questions on project closure. By the end of the book, you’ll have the knowledge you need to be confident on exam day.
Table of Contents (17 chapters)
Free Chapter
1
Acknowledgments
2
About the Author
15
Advert
16
EULA

Exam Essentials

Describe the sequencing process. Sequencing is the process of identifying dependency relationships between the project activities and scheduling activities in the proper order.

Name the two major relationships between dependent tasks. A predecessor is a task that exists on a path with another task and occurs before the task in question. A successor is a task that exists on a common path with another task and occurs after the task in question.

Name the four types of logical relationships. The four types of logical relationships are finish-to-start, start-to-start, start-to-finish, and finish-to-finish.

Know and understand the three most commonly used techniques to estimate activity duration. Expert judgment relies on the knowledge of someone familiar with the tasks. Analogous or top-down estimating bases the estimate on similar activities from a previous project. Parametric estimates are quantitatively based estimates that typically calculate the rate times the quantity...