If, for some reason, you need to import a Redmine project into Microsoft Project 2013, this recipe teaches you how to export Redmine issue data and import it to a Microsoft Project. Please keep in mind that Redmine-exported data can be used or imported in other software capable of CSV or Excel import.
Prepare Microsoft Project to open legacy file formats:
Start Microsoft Project and create a new blank project.
Go to File | Options.
Choose Trust Center.
Click the Trust Center Settings button.
Choose the Legacy Formats tab.
Choose Allow loading files with legacy or non-default file formats.
Close dialog boxes by clicking OK.
The first step is to export data from Redmine to a CSV file. To do it, perform the following steps:
Click on Issues in the main project menu.
Expand Options:

Choose and order the fields:

Save this as a new saved search for all projects so that you can reuse it later and for other projects if required. Click on the Save button...
Change the font size
Change margin width
Change background colour