In 2008 Oracle acquired Primavera Software, Inc., a leading provider of Project Portfolio Management (PPM) solutions for project-intensive industries.Primavera P6 Enterprise Project Portfolio Management is an integrated project portfolio management (PPM) solution comprising role-specific functionality to satisfy each team member's needs, responsibilities, and skills. It provides a single solution for managing projects of any size, adapts to various levels of complexities within a project, and intelligently scales to meet the needs of various roles, functions, or skill levels in your organization and on your project team.Oracle Primavera P6 Version 8: Project and Portfolio Management aims to show you all the features and functionality of the software thoroughly and clearly.With Oracle Primavera P6 Version 8: Project and Portfolio Management, readers will master the core concepts of Primavera P6 and the new features associated with version 8.This book is divided into two sections, in the first section we learn the fundamental concepts behind managing projects which include organizing projects, adding activities and relationships, assigning roles and resources, scheduling a project, and much more. In the second section we cover portfolio management and how to make the best use of the web client that includes working with portfolios, portfolio analysis, portfolio capacity planning, ROI, tracking performance, and lots more.
Table of Contents (25 chapters)
Oracle Primavera P6 Version 8: Project and Portfolio Management
Credits
About the Authors
About the Reviewers
www.PacktPub.com
Preface
Index

Settings at the activity level


Last but certainly not least, the activity level settings are paramount for schedule calculations. Most people know the activity settings and forget to look into all other settings when dates do not seem to calculate as expected.

Activities are the major component of a schedule, and there are several aspects to each activity that must be considered. Activity components can be categorized as Mandatory or Optional, and several of them together represent the chain that affects dates in P6.

Activity components that affect schedule calculation:

MANDATORY

Affects Dates

OPTIONAL

Affects Dates

WBS and OBS

 

Expenses

 

Activity ID and Description

 

Steps

 

Activity Type

Yes

Notebooks/Feedback

 

Duration

Yes

WP & Documents

 

Date (input)

Yes

Activity Codes

 

Calendar Assignments

Yes

Relationships

Yes

Duration Type

Yes

Constraints

Yes

Percent Complete Type

Yes

Role and Resource Assignments

Yes

Activity types

Each type will react differently to scheduling...