The CompTIA Project+ exam is designed for IT professionals who want to improve their career trajectory by gaining certification in project management specific to their industry. This guide covers everything necessary to pass the current iteration of the Project+ PK0-004 exam. The CompTIA Project+ Certification Guide starts by covering project initiation best practices, including an understanding of organizational structures, team roles, and responsibilities. You’ll then study best practices for developing a project charter and the scope of work to produce deliverables necessary to obtain formal approval of the end result. The ability to monitor your project work and make changes as necessary to bring performance back in line with the plan is the difference between a successful and unsuccessful project. The concluding chapters of the book provide best practices to help keep an eye on your projects and close them out successfully. The guide also includes practice questions created to mirror the exam experience and help solidify your understanding of core project management concepts. By the end of this book, you will be able to develop creative solutions for complex issues faced in project management.
Table of Contents (13 chapters)

Questions

  1. You are the project manager for a large installation project. Your key stakeholders are discussing the best ways to manage changes to the schedule. Which is the best document to refer them to?
    • The schedule baseline
    • WBS
    • The schedule management plan
    • The schedule
  2. You are working with your team to decompose the work packages of your WBS down to the task list. What other document will you be preparing?
    • Milestone list
    • Sequenced tasks
    • The schedule
    • An outline
  3. You have just completed the development of the task list and your milestones for the project. What step do you take next?
    • Create the schedule
    • Sequence tasks
    • Estimate resources
    • Estimate durations
  4. Bill is on your core team for your new server installation project. As you are working together on the beginning of the schedule creation, Bill mentions that you will need complete all the tests on the new equipment and...