The CompTIA Project+ exam is designed for IT professionals who want to improve their career trajectory by gaining certification in project management specific to their industry. This guide covers everything necessary to pass the current iteration of the Project+ PK0-004 exam. The CompTIA Project+ Certification Guide starts by covering project initiation best practices, including an understanding of organizational structures, team roles, and responsibilities. You’ll then study best practices for developing a project charter and the scope of work to produce deliverables necessary to obtain formal approval of the end result. The ability to monitor your project work and make changes as necessary to bring performance back in line with the plan is the difference between a successful and unsuccessful project. The concluding chapters of the book provide best practices to help keep an eye on your projects and close them out successfully. The guide also includes practice questions created to mirror the exam experience and help solidify your understanding of core project management concepts. By the end of this book, you will be able to develop creative solutions for complex issues faced in project management.
Table of Contents (13 chapters)

Chapter 1 – Introduction to the CompTIA Project+ Exam (PK0-004)

  1. Control charts.
  2. Project B, because its NPV is a positive value.
  3. A project initiator or sponsor.
  4. Regulations are approved by a recognized body and employ rules and guidelines that should be followed.
  5. It authorizes the project and the use of organizational resources to meet project requirements.
  6. Organize meetings to identify and resolve misunderstandings between team members, to avoid interface problems, disintegration, and costly rework early in the project.
  7. The interpersonal relationships between team members are their private issue. You should not interfere.
  8. Control scope-creep completely.
  9. The cost baseline will be updated, and the new baseline will be the basis for future earned value analysis.
  10. Fast tracking.