MAT
In the MAT, the OTS supplier will need to verify to the contractor that they have built the correct process model. If the MAT is successful and the contractor signs it off, it gives the supplier the green light to move to the next step and integrate the process model into the ICSS. It is very important to ensure the model is behaving correctly before moving to the next step.
The main points to ensure during the MAT are as follows:
- Ensure the correct documentation is used to build the process model.
- Ensure the correct H&MB is used to build the process model.
- Ensure the correct datasheets have been used to build the process model.
- Ensure the correct thermodynamic methods are used to build the process model.
- Ensure the correct components are used to build the process model
- Ensure the steady state model has been running in a steady condition for at least 12 hours.
- Ensure the PAMs are communicating with each other and the connections are stable...