FAT
In the FAT, the supplier will need to verify and show the contractor that they have built the system right.
In the FAT, the OTS supplier will need to show the contractor the following:
- All model issues from the MAT have been addressed.
- All the correct documentation has been used to build the OTS.
- All the correct software versions have been used to build the OTS.
- All the correct hardware has been used to build the OTS.
- All the correct software licenses have been installed and are working on the OTS.
- All the agreed ICs have been delivered and are working correctly on the OTS.
- The system can perform the agreed process operations, and they are usually as follows:
- Normal plant shutdown
- Normal plant startup
- Agreed model stress tests (such as emergency shutdown and 12-hour OTS runs).
- Agreed instructor functionality checks.
- Agreed contractor custom tests.
All the preceding points will need to be signed off by the contractor so the FAT...