(More than one answer may be correct)
- Scrum allows for re-estimating tasks based on growing insights. Which scrum team member is responsible for updating the estimates of the work during the Sprint?
- Development team
- Scrum master
- Product owner
- None of this
- Who are involved in the scrum?
- Development team
- Scrum master
- Product owner
- None of this
- What are the artifacts of the scrum?
- Sprint backlog
- Product backlog
- Velocity chart
- All of this
- What kind of software development projects can be executed by a scrum framework?
- Customer projects
- Complete software packages
- All kinds of software development
- None of this
- Where are the customer requirements stored?
- Product backlog
- Sprint backlog
- Database
- With scrum product owner
- What is important for all scrum projects?
- Self-organization
- Clear hierarchy in the company
- Communication
- Continuous improvement