In 2008 Oracle acquired Primavera Software, Inc., a leading provider of Project Portfolio Management (PPM) solutions for project-intensive industries.Primavera P6 Enterprise Project Portfolio Management is an integrated project portfolio management (PPM) solution comprising role-specific functionality to satisfy each team member's needs, responsibilities, and skills. It provides a single solution for managing projects of any size, adapts to various levels of complexities within a project, and intelligently scales to meet the needs of various roles, functions, or skill levels in your organization and on your project team.Oracle Primavera P6 Version 8: Project and Portfolio Management aims to show you all the features and functionality of the software thoroughly and clearly.With Oracle Primavera P6 Version 8: Project and Portfolio Management, readers will master the core concepts of Primavera P6 and the new features associated with version 8.This book is divided into two sections, in the first section we learn the fundamental concepts behind managing projects which include organizing projects, adding activities and relationships, assigning roles and resources, scheduling a project, and much more. In the second section we cover portfolio management and how to make the best use of the web client that includes working with portfolios, portfolio analysis, portfolio capacity planning, ROI, tracking performance, and lots more.
Table of Contents (25 chapters)
Oracle Primavera P6 Version 8: Project and Portfolio Management
Credits
About the Authors
About the Reviewers
www.PacktPub.com
Preface
Index

Structuring the WBS of the project


As mentioned in Chapter 3, Organizing your Projects with EPS, OBS, and WBS, the WBS is used to organize and manage the work in your project. Also in that chapter we went over how to create and organize WBS. Now let's look closer at other properties of the WBS.

To see the WBS details, open up the WBS screen, right-click, and choose WBS Details. This will bring up a tabbed window as shown in this screenshot. If you do not see all of the tabs, right-click on the top of the Tab window and choose Customize WBS Details….

General

The General tab shows high-level details about the selected WBS element. WBS Code and WBS Name can be edited here. See more about the WBS in Chapter 3. Status can be set to Active, Inactive, Planned and What-if. Responsible Manager is the OBS element responsible for this WBS item, and governs which users have which security access to the activities in this WBS item.

Anticipated Start is set during the planning stage, and does not figure...