At this point, you should be able to augment your implementation task list with dates that include equipment purchases, upgrades, installation, and configuration. Using Not Just Widgets as an example, the following is a sample list of infrastructure-specific tasks:
Task |
Description / Notes |
Start |
Finish By |
---|---|---|---|
Order/receive new server for Dynamics GP |
NJW will be getting a new dedicated server for Dynamics GP. |
April-20-2013 |
May-15-2013 |
Order and receive new desktops or upgrades |
Several desktops are old and were planned to be replaced soon anyway. A few other desktops are fine, but will be upgraded with more RAM. |
May-14-2013 |
Jun-16-2013 |
Configure new server and install SQL Server |
Includes installation and configuration of Windows Server 2012 and SQL Server 2012 and all the latest service packs for both. |
May-16-2013 |
May-28-2013 |
Network share for Dynamics GP |
Set up a network location for all shared files for Dynamics GP. Make sure to add this... |