Book Image

Learning Microsoft Project 2019

By : Srikanth Shirodkar
Book Image

Learning Microsoft Project 2019

By: Srikanth Shirodkar

Overview of this book

Microsoft Project is one of the most popular project management tools for enterprises of all sizes thanks to its wide variety of features such as project scheduling, project budgeting, built-in templates, and reporting tools. Learning Microsoft Project 2019 will get you started with the basics and gradually guide you through the complete project life cycle. Starting with an overview of Microsoft Project 2019 and a brief introduction to project management concepts, this book will take you through the different phases of project management – initiation, planning, execution, control, and closure. You will then learn how to identify and handle problems related to scheduling, costing, resourcing, and work allocation. Understand how to use dynamic reports to create powerful, automated reports and dashboards at the click of a button. This Microsoft Project book highlights the pitfalls of overallocation and demonstrates how to avoid and resolve these issues using a wide spectrum of tools, techniques, and best practices. Finally, you will focus on executing Agile projects efficiently and get to grips with using Kanban and Scrum features. By the end of this book, you will be well-versed with Microsoft Project and have the skills you need to use it effectively in every stage of project management.
Table of Contents (32 chapters)
1
Section 1: The Iron Triangle – a Quick Primer for Project Management
3
Section 2: Project Initiation with Microsoft Project
8
Section 3: Project Planning Like a Pro!
13
Section 4: Project Execution – the Real Deal
15
Chapter 11: Overallocation – the Bane of Project Managers
18
Section 5: Monitoring and Control with Microsoft Project
23
Section 6: Project Closure with Microsoft Project
Appendix A: Using This Book as a Textbook
Appendix C: Keyboard Shortcuts
Appendix D: Glossary

Working with date constraints

It is highly recommended that you work in the automatic scheduling mode of Project. All the useful scheduling features and tools that you have been learning about so far are only applicable in the automatic scheduling mode of Project. But sometimes, you may have hard deadlines, such as in the space mission project example from the start of this chapter, where, within a certain precise date, certain mission experiments should be finished, and other new ones should be started.

There are two ways to incorporate specific dates into your project:

  • Set manual scheduling mode on for that particular task and set the start date, thereby taking over the responsibility of managing all its parameters. The effect of doing so would effectively be comparable to working with Excel for that task. Moreover, it may also present hard-to-discover bugs in the schedule. Since this is not the recommended technique, we will not dwell on this option.
  • Stay within...